Law 

Legal News [February 2025]: Rejection of a claim for the grant of necessary access

The Supreme Court, in a series of its latest rulings, addressed key issues of civil law – from the ‎rejection of a claim for the grant of necessary access due to gross negligence, to liability arising from ‎operational collisions under Hungarian law, and issues surrounding the placement of a ‎communication path on another's property, to the transfer of the right to a contractual penalty when ‎a claim is assigned to an insurer. Some cases were also remanded for further proceedings with the ‎requirement for more thorough examination.‎

  • The Supreme Court of the Czech Republic, in its judgment ref. no. 22 Cdo 1833/2024, dealt with the ‎issue of the rejection of a claim for the grant of necessary access, as the claimant allegedly ‎caused the lack of access to the acquired properties from a public path through gross ‎negligence under § 1032 paragraph 1 letter b) of the Civil Code. The dispute involved the situation ‎where the claimant acquired the relevant property connected to a purpose-built communication ‎path while proceedings on granting necessary access were ongoing. The appellate court concluded ‎that at the time of acquiring the properties, the claimant was aware of the absence of a private law ‎title authorizing access from the public path. It also took into account that, at the time of acquiring ‎the properties, the claimant was a businesswoman, among other things, in the field of real estate ‎activities. The Supreme Court concluded that it is essential to consider that the claimant had ‎ensured factual access to the acquired properties at the time of acquisition (no one prevented the ‎claimant from accessing the properties). In such a case, it cannot be ruled out that the claimant’s ‎access was ensured (at least temporarily) based on public law authorization deriving from the ‎existence of the purpose-built communication path located in a closed area under § 7 paragraph 2 of ‎the Roads Act. In other words, if the applicant for necessary access had access from the public path ‎to the acquired properties based on public law authorization (possibly temporarily), this fact can be ‎considered while assessing their actions in connection with securing access as a factor in their ‎favor. The Supreme Court further noted that at the time of the claimant’s acquisition of the ‎properties, established case law providing solutions for the legal issue of ensuring access to a ‎structure not adequately connected to a public path tended to assess the applicant’s culpable ‎action rather leniently and reject undesirable actions into setting an appropriate compensation for ‎establishing necessary access. For these reasons, the Supreme Court concluded that the appellate ‎court’s decision that the claimant caused the lack of access from the public path to the properties ‎due to gross negligence under § 1032 paragraph 1 letter b) of the Civil Code was incorrect.‎
  • In its judgment, ref. no. 25 Cdo 685/2023, the Supreme Court addressed the issue of liability from ‎operational collisions of means of transport under Hungarian civil law, which had not been ‎addressed by the Supreme Court before. The dispute involved a traffic accident in Hungary where ‎a Hungarian vehicle, insured for liability for damage caused by motor vehicle operation with the ‎defendant (ČSOB), collided with the claimant’s vehicle. The first-instance and appellate courts ‎judged that the defendant was exempted from the duty to compensate the claimant for the damage. ‎The Supreme Court agreed with the claimant that even incorrect application of foreign law can ‎establish the admissibility of an appeal, as the opposite approach would lead to the ‎unacceptable denial of justice and disadvantage those parties in cases applying foreign law versus ‎those whose cases do not involve foreign law. Furthermore, the Supreme Court found that neither ‎the conclusions of the first-instance court nor the appellate court were consistent with the ‎interpretation of Hungarian law within Hungary, thus remanding the case back to the first-instance ‎court for further proceedings.‎
  • In its judgment, ref. no. 22 Cdo 2503/2024, the Supreme Court dealt with the possibility of placing a ‎land communication path as an independent entity in legal terms on another’s land without ‎the owner’s consent. The case involved the establishment of a local communication path without ‎the original owner’s consent, which was subsequently reclaimed by the original owner in restitution. ‎The Supreme Court reminded that if a local communication path, which is a structure in terms of civil ‎law, and thus a legal entity, leads through land owned by a different person than the owner of the ‎local communication path, it is necessary to distinguish between the question of the right to have a ‎communication path structure on another’s land and a potential claim arising from unauthorized ‎placement of the communication path structure on another’s land on one hand, and the right to use ‎this local communication path on the other hand. It is necessary to examine whether (if) the local ‎communication path was established under any legal title. If it was established without ‎authorization, i.e., without a legal title, the reclaiming owner has the right to demand the cessation of ‎such use. The case was remanded to the appellate court for further consideration of the ‎aforementioned issue.‎
  • In its decision ref. no. 23 Cdo 1887/2023, the Supreme Court addressed whether, under § 2820 ‎paragraph 1 of the Civil Code, the right to a contractual penalty for the debtor’s delay with the ‎payment of the insured claim, which arises after the payment of the insurance benefit, also ‎transfers to the insurer. The Supreme Court confirmed that when the claim is transferred to the ‎insurer under § 2820 paragraph 1 of the Civil Code, it includes all rights and securities belonging to it. ‎This means that along with the claim, the insurer acquires the right to a contractual penalty, which ‎serves to secure the fulfillment of the debt. Since the contractual penalty is directly tied to the ‎claim, its fate cannot be separated from the fate of the claim itself. Quantitative limitation on the ‎transfer of the claim, i.e., up to the amount of the paid insurance benefit, does not apply to the ‎contractual penalty arising after this transfer. The insurer can then assert claims for the contractual ‎penalty under § 2048 of the Civil Code even after the statutory assignment occurs. If the debtor ‎continues to default on their debt after the payment of the insurance benefit to the entitled party, i.e., ‎from the moment of the claim’s transfer under § 2820 paragraph 1 of the Civil Code, the insurer is ‎entitled to the contractual penalty accrued for this period.‎
Legal News dReport newsletter

Upcoming events

Seminars, webcasts, business breakfasts and other events organized by Deloitte.

    Show morearrow-right